Concrete & Masonry

Concrete Footing Calculator

Estimate volume and optional 80 lb bag equivalents for rectangular footings using length, width, depth, quantity, and waste allowance.

Last reviewed:

Project measurements

Measurement system

This calculator measures entered rectangular footings only. It does not recommend footing size or interpret building codes. See the disclaimer.

How to use this calculator

  1. Choose a measurement system.
  2. Enter the rectangular length, width, and depth of one footing.
  3. Enter the number of identical footings.
  4. Add waste and calculate the total volume.

How the calculation works

One footing’s rectangular volume is multiplied by the footing count. Waste is then applied to the combined volume, which is converted to cubic yards and cubic meters.

Formula

One footing = length × width × depth
Base volume = one footing × quantity
Adjusted volume = base volume × (1 + waste % ÷ 100)

Worked example

Three footings measuring 10 ft × 2 ft × 1 ft contain 60 cubic feet. With 5% waste, the estimate is 63 cubic feet, or about 2.33 cubic yards.

How footing size drives the order

Footing volume grows with both width and depth, so a modest change in the trench has a large effect on the truck. The table gives the concrete in each 10 linear feet of continuous footing at four cross-sections. These are volume illustrations only, not recommended sizes. The footing size for your building comes from the plans, the soil, and the local code.

Width × depthCubic feet per 10 ftCubic yards per 10 ft
12 in × 6 in5.000.19
16 in × 8 in8.890.33
20 in × 10 in13.890.51
24 in × 12 in20.000.74

Second scenario: a continuous footing around a small building

Take a 20 ft by 24 ft rectangle measured along the center of the footing, with a section 16 inches wide and 8 inches deep. Enter one footing that is 88 feet long, since 2 × (20 + 24) = 88. The volume is 88 × 1.3333 × 0.6667, or 78.22 cubic feet. With 5% waste the order is 82.13 cubic feet, or 3.04 cubic yards.

Measuring along the centerline matters. If you add the four outside edge lengths, the corners are counted twice and the total comes out too high.

Why trenches take more than the drawing

A footing poured against hand-dug earth fills every dip and soft spot, so the true volume is usually larger than width times depth. Trench collapse and overbreak at the bottom both add concrete. That is the main reason to choose a higher waste allowance for earth-formed footings than for a footing placed in straight wooden forms. A home-inspector association describes typical minimums of 12 inches wide and 6 inches thick, with the bottom at least 12 inches below grade and below the local frost depth, but your building department sets the rules that apply to you.

Mistakes to catch before the pour

  • Entering a depth of 8 in a field that expects feet. Use the inches field, or enter 0.67.
  • Treating several different footings as identical. A stepped footing or a footing with a pad needs separate entries.
  • Leaving out the footing under a chimney, a porch, or a column pad.
  • Ordering before the inspector has seen the trench, if your area requires an inspection.

Where professional input is required

Footings carry the weight of the structure, so size and depth are an engineering and code question. A structural engineer or your local building department can confirm the width, depth, reinforcement, and frost protection. This page tells you how much concrete fills the shape you have chosen.

Project considerations

  • This calculator measures entered geometry only.
  • It does not determine footing dimensions, reinforcement, bearing capacity, or code compliance.
  • Measure each differently sized footing as a separate calculation.

Frequently asked questions

Does this calculator size a footing?

No. Enter dimensions established for the project; the result is volume only.

Are round piers included?

No. This tool is specifically for identical rectangular footings.

References

Published sources for context. They are not used in the calculation.