Concrete & Masonry

Concrete Column Calculator

Estimate concrete volume for one or more identical round columns, such as tube-form piers, from diameter and height, with an adjustable waste allowance.

Last reviewed:

Project measurements

Measurement system

This calculator measures entered round columns only. It does not size columns or footings or interpret building codes. See the disclaimer.

How to use this calculator

  1. Choose US customary or metric measurements.
  2. Enter the column diameter and height, using the inside diameter of the tube or form.
  3. Enter how many identical columns you are pouring.
  4. Add a waste allowance and calculate the concrete volume.

How the calculation works

A round column is a cylinder, so its volume is the area of its circular cross-section times its height. The calculator finds the volume of one column, multiplies it by the number of identical columns, and applies the waste allowance. It measures geometry only and does not size columns or footings.

Formula

One column = π × (diameter ÷ 2)² × height
Total with waste = one column × number of columns × (1 + waste % ÷ 100)

Worked example

A 12 in diameter column 8 ft tall holds about 6.28 cubic feet (π × 0.5² × 8). Four columns with 5% waste need about 26.39 cubic feet, or 0.98 cubic yards, which is about 44 bags of 80 lb mix at 0.6 cubic feet per bag.

Volume by tube diameter

Volume grows with the square of the diameter, which makes the tube size the biggest lever in this calculation. The table gives one straight column per tube diameter, with the volume per foot of height and the volume of an 8 foot column. It uses the formula on this page.

Inside diameterCubic feet per footCubic feet in 8 ft
8 in0.3492.79
10 in0.5454.36
12 in0.7856.28
16 in1.39611.17
18 in1.76714.14
24 in3.14225.13

Second scenario: six short piers

Six tube piers, each 10 inches across and 3 feet tall, hold 0.5454 × 3 = 1.636 cubic feet each, or 9.817 cubic feet together. With 10% waste the order is 10.80 cubic feet, which is 0.40 cubic yards. In 80 lb bags at 0.6 cubic feet each that is about 18 bags. At that size, mixing by the bag is realistic, but each pier should be placed and consolidated before the next one stiffens.

Inside diameter and tube behavior

Use the inside diameter printed or measured on the form, because that is the shape the concrete fills. Tube forms made of fiber can bulge under the pressure of wet concrete, and a pier poured into a hole that is wider than the tube will also take more. Both are reasons for a waste allowance on the high side of what you would use for a straight, formed slab.

Common mistakes

  • Entering the diameter in feet when the tube is sold in inches. A 12 in tube is 1 foot, and typing 12 gives a column 144 times too large.
  • Using the radius where the field asks for diameter.
  • Counting the buried footing as part of the column. Calculate that with the footing page.
  • Forgetting that a column poured over a flared base needs separate arithmetic for the flare.

Posts, piers, and what a professional decides

A pier under a deck, porch, or building carries load, and its diameter, depth below the frost line, reinforcement, and connection to the post are set by the plans and the local code. Many jurisdictions inspect pier holes before the pour, and the free national 811 service should be called a few days before any digging so buried utilities are marked. The calculator can tell you the volume of the shape you chose and nothing about whether the shape is adequate.

Project considerations

  • Use the inside diameter of the tube or form, because that is the shape the concrete fills.
  • Flared or bell-shaped bases, footings below the column, and reinforcement are not included. Calculate those parts separately.
  • Column size, depth, and reinforcement come from plans, local code, and the project engineer, not from this tool.

Frequently asked questions

Can I use this for tube-form piers?

Yes, as long as the column is a straight cylinder. Enter the form diameter and the height to fill. A footing poured below the tube should be calculated with the footing calculator.

Why does a larger diameter add so much concrete?

Volume grows with the square of the diameter. Doubling the diameter multiplies the concrete for the same height by four.